How do I roster security guards under the Montenegrin Labour Law?
Short answer
- Take the 40-hour week as the baseline and commit the shift schedule to paper.
- Publish it no later than seven days before it applies, unless urgency makes that impossible.
- Between two working days leave 12 hours, and add a weekly rest of 24 hours or more.
- Count 22:00 to 06:00 as night work, and never keep one guard on nights for longer than a single week at a time.
- Authorise any overtime in writing ahead of time, and keep presence and hours on record.
What the law says
- Full time (art. 61): full-time work is 40 hours a week unless the law says otherwise.
- Schedule (art. 67): an employer that works in shifts must adopt a written decision on the schedule and the shifts, and must announce it at least seven days ahead except in urgent cases.
- Rest (arts. 75 and 76): an employee has at least 12 hours of continuous rest between two working days and a weekly rest of at least 24 hours added to it, and where the work requires, the employer sets other days for it.
- Break (art. 73): a full-time employee is entitled to a break of at least 30 minutes during the working day, counted as working time.
- Night work (arts. 70 and 71): night work runs from 22:00 to 06:00, the employer must inform the labour inspection of it, and in shifts that include nights the replacement must let an employee work nights for one week at most in a row.
- Overtime (art. 64): overtime is introduced by a written decision before it starts, may not exceed 48 hours a week on average over four months and must be reported to the labour inspector within three days.
- Records (art. 19, art. 142): the employer must keep a record of employees that includes presence at work, and if it does not, the burden of proof in a dispute about working time is on the employer.
Practical examples
- A Podgorica operator staffs a mall in three shifts. The monthly rota goes on the staff board eight days early, and whoever works nights is rotated off after a week.
- In Tivat a guard clocks out at 06:00 and the draft puts him back on at 14:00. The planner spots only eight hours of rest, well under 12, and moves the start.
- For a weekend festival on the Budva coast the manager needs extra hands, signs an overtime order first and notifies the inspector within three days.
Common mistakes
- Pinning the schedule up the evening before when nothing was urgent.
- Watching only weekly totals and overlooking the 12-hour gap between two days.
- Agreeing overtime by word of mouth and writing it up later.
- Applying the 2021 text with no look at later amendments or the collective agreement.
- Assuming 4guards applies Montenegrin limits automatically, when those thresholds are values you set.
How 4guards helps
- Each site has a shift grid. On Plus and above, saving a shift tests for overlaps, daily rest (default 12 hours), the longest allowed shift (default 12 hours) and the expiry date typed on the guard's record. A rolling seven-day total above a chosen number of hours (default 48) raises a warning.
- These are your own settings, not statute. Align them with the Labour Law, the client contract and any collective agreement; per account, a breach either blocks saving or just warns.
- Left unchecked: the weekly rest day, night-work rules, the seven-day announcement and overtime decisions.
- A coverage report lists, for a site and a period, every interval where fewer guards are planned than posts demand. You open it yourself; nothing is pushed out.
- A dispatch board shows running shifts, who has checked in, who is late and which posts are empty.